CONTENTS
ACKNOWLEDGEMENT………………………………………………...
ABSTRACT………………………………………………………………..
LIST OF ABBREVIATIONS……………………………………………..
WORKING SCHEDULDES………………………………………………
SALIENT FEATURES……………………………………………………
LIST OF FIGURES………………………………………………………..
LIST OF TABLES………………………………………………………….
1.
INTRODUCTION
1.1 Introduction
to the Subject…………………………………………..
1.2 Principle
of Surveying
1.3 Objectives
of Surveying
1.4 Project
Area
1.4.1 Location and Accessibility
1.4.2 Topography and Geology
1.4.3 Rainfall, Climate,
Vegetation
1.4.4 Others
2.
TOOPGRAPHICAL SURVEY
2.1 Brief
Description of the area
2.2 Objectives
2.3 Norms(Technical
Specifications)
2.4 Equipment
2.5 Methodology
2.5.1 Reconnaissance
2.5.2 Traversing
2.5.2.1 Major Traverse
2.5.2.2 Minor Traverse
2.5.2.3 Balancing the Traverse
2.5.3
Detailing
2.5.4
Leveling
2.5.5
Two-Peg Test
2.5.6
Contouring
2.5.7
Computation and Plotting
2.6 Comments
and Conclusions
3.
BRIDGE SITE SURVEY
3.1 Objectives
3.2 Brief
Description of the area
3.3 Hydrology ,Geology of the area
3.4 Norms(Technical Specifications)
3.5 Equipment
3.6 Methodology
3.6.1 Site
Selection
3.6.2 Topographic
Survey
3.6.3 Longitudinal Section
3.6.4 Cross Section
3.6.5 Levelling
3.6.6 Detailing
3.7 Computation
& Plotting
3.8 Comments
& Conclusions
4.
ROAD ALIGNMENT AND GEOMETRIC DESIGN
4.1 Brief
Description of the area
4.2 Objectives
4.3 Hydrology,
Geology and soil
4.4 Norms(Technical
specifications)
4.5 Equipment
4.6 Methodology
4.6.1 Reconnaissance
4.6.2 Horizontal Alignment
4.6.3 Vertical
Alignment
4.6.4 Levelling
4.6.5 Longitudinal
Section
4.6.6 Cross
Section
4.6.7 Topographic
survey of road corridor
4.7 Computation
and Plotting
4.8 Comments
& Conclusions
BIBLIOGRAPHY
5.
OBSERVATIONS AND CALCULATIONS
6.
MAPS AND DRAWINGS
LIST OF ABBREVIATIONS
AP -Apex Point
BC-Beginning of Curve
BM-Bench Mark
BS-Back Sight
CP-Common Point
D M S-Degree Minute Second
D/S-Down Stream
EC-End of Curve
EDM-Electronic Distance Measurement
FL-Face Left
FR-Face Right
FS-Fore Sight
GP-Ground Point
HI-Height of Instrument
IS-Intermediate Sight
IP-Intersection Point
IS-Intermediate Sight
Recce-Reconnaissance
RL-Reduced Level
TBM-Temporary Bench Mark
T M B-Top Middle Bottom
TP-Turning Point
U/S-Up Stream
VCR-Vertical Circle Reading
HCR- Horizontal Circle Reading
TL-Tangent Length
LC-Length of Curve
BC-Beginning of Curve
MC-Middle of Curve
EC-End of Curve
GP-Ground Point
BL-Bank Level
HFL-High Flood Level
BR-Bridge
CL-Centre Line
R-Road
GW-Gabin Wall
TR-Tree B-Building
To-Toilet
W-Wall
Fe-Fence
GT-Gate
LB- Left Bank
RB- Right Bank
WORKING SCHEDULE
S.N |
Day |
Survey
Field Work |
1. |
17th Baisakh |
v
Reconnaissance surveying for major traverse v
Marking major station v
Angle measurement of major and minor stations v
Two-way linear measurement(EDM) |
2. |
18th Baisakh |
v
Angle Measurement v
Two-Peg Test v
RL Transfer from TBM to CP1 |
3. |
19th Baisakh |
v
RL Transfer on pegs v
Calculations |
4. |
20th Baisakh |
v
Calculations and Plotting v
Detailing |
5. |
21st Baisakh |
v
Detailing |
6. |
22nd Baisakh |
v
Detailing |
7. |
23rd Baisakh |
v
Reconnaissance for bridge site survey v
Marking of Stations in Upstream and downstream v
Angle measurement by Triangulation v
Peg to peg RL Transfer by Fly and reciprocal
Leveling |
8. |
24th Baisakh |
v
Profile and Cross Section levelling v
Detailing of river site |
9. |
25th Baisakh |
v
Reconnaissance for road alignment v
IP Marking and setting out of simple circular
curve v
RL transfer of IPs by Fly levelling |
10. |
26th Baisakh |
v
Profile and Cross section leveling 25 m on
each side of road |
SALIENT FEATURES
Name of the Project: Survey
Camp 2081
(A)Description of the
Project:
Location:
Ø
Province: Koshi
Ø
District: Sunsari
Ø
Municipality: Dharan
§
Latitude:28.6˚N
§
Departure:87.28˚E
Site: Campus Area for detailed surveying, Shardu
River for bridge and road alignment surveying.
Geographical features:
Ø
Terrain: Plain and rolling
Ø
Climate: Mild temperature
Ø
Geology: Plain region with small undulations
composed of gravels, boulders etc
Ø
Vegetation: Good
(B)Description of works:
(a)Traversing:
Ø
No. Of Major Traverse stations: 13 (including
CP1 and CP2)
Ø
No. Of minor loops: 1
Ø
No. Of Minor traverse stations: 6
Ø
Perimeter: 1324.976
Ø
Longest leg length: 139.508(H3-H4)
Ø
Shortest leg length: 74.401(H8-H9)
Details of the data taken are in the observation
sheet.
Scale:
Ø
Topographic map: 1:500
Ø
Contour interval:0.5m for topographical survey
and 1m for road and bridge traverse
Detailing:
Area: The major traverse contains Campus
area, staff block, Park and trees etc.
(b)Road Alignment:
Ø
Road Type: Village Road
Ø
Surface: Gravel
Ø
Length of the road: 720m
Ø
No. Of intersection points: 6
Ø
Cross section: 25m left and 25m right on both
sides from the centerline.
Ø Longitudinal section: In every 20m of the
length for road alignment survey.
Details of the data
taken are in the observation sheet.
Scale:
Ø Topographic
map: 1:500
Ø Contour interval: 0.5 m
(c)Bridge Site Survey:
i) Bridge Span
ii) Cross
section: 300m on upstream and 200m on downstream
Details of
data taken are in the observation sheet.
Scale:
Ø Topographic
map: 1:500
Ø Cross
sectioning: Horizontal= 1:500
Ø Vertical=1:50
Ø Contour
Interval=1m
LIST OF FIGURES
Figure 1: Open
Traverse……………………………………………………………
Figure 2: Closed
Traverse………………………………………………..…………
Figure 3: Closing Error
AA'……………………………………………..…………
Figure 4: Total station and its
parts……………………………………………...…
Figure 5: Two-peg
Test……………………………………………………….……
Figure 6: Triangulation ……………………………………………………………
Figure 7: Reciprocal Levelling ………………………………………….…………
Figure 8: Simple Circular
Curve……………………………………………………
Figure 9: Rankine’s
method…………………………………………………………
Appendix A: Field observations and
calculations
1. Topographic
Survey
1.1 Two
Peg Test
1.2 RL
transfer from BM to TBM
1.3 Linear
and angular measurement of major and minor stations
1.4 Traverse
computation (major and minor stations)
1.5 RL
transfer from TBM to major station
1.6 RL
transfer from station to other traverse stations
1.7 Detailing
2. Bridge
Site Survey
2.1
Triangulation survey sheet
2.2
Independent co-ordinates of stations
2.3
Fly levelling from BM to station F0 and all
other stations
2.4
Reciprocal levelling
2.5
Tachometry survey
3. Road
Alignment
3.1
Horizontal alignment fixing of Canal
3.2
Differential levelling of Canal
Appendix B: Maps, Drawings and
Graphs
1. Topographic
Map of IOE Purwanchal Campus (Dharan-8, Sunsari)
2. Topographic
Map of Bridge site (Sardu Khola, Dharan-17)
3. Profile
and Cross-section of Weir Site ( Sardu Khola, Dharan-17)
4. Road
Alignment and Detailing (Sardu Khola, Dharan-17)
5. Profile
and Cross-section of Roadsite ( Sardu Khola, Dharan-17)
CHAPTER:1
1.1 INTRODUCTION
Surveying is an art and science of determining the
relative positions of point on above or beneath the surface of the earth by
means of angular and linear measurements. The main objective of surveying is to
prepare plans and maps of areas. Thus, the subject emerges out to be the most
important before and during all engineering works like civil engineering works
such as designing and construction of highways, water supply systems,
irrigation projects, buildings etc.
The process of
surveying consists of fieldwork of taking measurements and office work of
continuing and drawing necessary to the purpose of survey. The fieldwork is the
vital part for any kind of survey. As a surveyor, he/she must have sound
knowledge, instrument handling skills, personal traits of friendship,
sociability by rational and logical, be able to lead and command, etc.
The B.E. Survey Camp 2081 organized by the Department
of Civil Engineering, I.O.E., Purwanchal Campus is a part of the four-year
Bachelor's degree in Civil Engineering course, third year first semester,
carrying a total of 100 marks. The total duration of our survey camp was 10
days, from 17th of Baisakh to 26th of Baisakh, 2081. This is a detailed report
of the works performed by group H during the camp period. It briefly explains
the working procedures and technique along with the observations, calculations,
and methods of adjustment of error. In addition, it also contains the main
problem faced during work and their solution, results of all calculations.
The work done
during the camp duration can be categorized into:
1. Topographical
survey
2. Bridge site
survey
3. Road
alignment survey
1.1 Principle of Surveying
The fundamental
principles of surveying are:
(a) Working from whole to part: It is very essential to establish first a system of
control points with higher precision. For horizontal control, the points are
established by triangulation or by precise traversing. To do this
triangulation, the area to be surveyed is divided into large triangles which
are surveyed with the greatest accuracy. They are further divided into small
triangles which are surveyed with less accuracy. The objective of this system
of working is to prevent the accumulation of error and to control the localize
minor errors.
(b) Location of a point by measurement from two control
points: The relative position of
points to be surveyed should be located by the measurement from at least two
(preferably three) points of reference, the position of which have already been
fixed.
(c) Consistency of work: Keeping consistency in method, instrument and observer, the survey
work of desired level of accuracy can be obtained.
(d) Independent check: Every measurement taken in the field must be checked by some
independent field observation so that the mistake is not passed unnoticeably.
(e)
Accuracy
required: Proper method and proper
instrument should be used depending upon the amount of accuracy required.
Accuracy of angular and linear values should be compatible.
1.2 Objectives
of Survey Camp:
The main objective of the survey camp is to
provide a basic knowledge of practical implementation of different surveying
works. It helps to build up the self-confidence level by implementing different
surveying works.
Other
objectives of the camp can be further listed as follows:
Ø
Horizontal control and vertical control survey
practices and produces topographic map in coordinate system.
Ø Linear segment survey practice through Road Alignment
Survey.
Ø
Practices of horizontal control and vertical
control survey surrounding the river through bridge site survey.
1.4 Project Area:
IOE PURWANCHAL CAMPUS DHARAN FOR TOPOGRAPHICAL SURVEY.
SARDU KHOLA AREA FOR BRIDGE AND ROAD SITE SURVEY.
1.4.1 Location and Accessibility:
Dharan
is situated on the foothills of the Mahabharat Range in the north with its
southern tip touching the edge of the Terai region at an altitude of 1148 ft
(349m). Dharan bazaar grew up near Phusre where the old walking route to
Dhankuta and a large part of the Eastern hills left the plains with the ascent
of Sanghuri Danda. The area to be surveyed for topographic survey is area under
IOE Purwanchal Campus. Being the college premises, our project area was quite
suitable and easily accessible.
Similarly,
Sardu Khola, famous for the Weekly shramdaan in Dharan lead by Harka Sampang,
is located in west of Dharan. This is the torrential stream which cause
disaster in the downstream during rainy season. Campus has made bus available
for travel to and from site. Thus, our project area was quite suitable and
easily accessible. The journey from Kathmandu to Sardu Khola takes about 30
minutes by bus.
Ø Country: Nepal
Ø Province no.: 01
Ø Province Name: Koshi
Ø District: Sunsari
Ø Municipality: Dharan
Ø Ward No.: 15
➢
Ward No.: 16
Ø Location: IOE Purwanchal Campus ➢Location: Sardu Khola
1.4.2Topography and Geology:
IOE
Purwanchal Campus occupies areas of 34-13-11.75 Bigahas in convenient unit,
which is equivalent to about 234,870.53 square meters. It is adjacent to
Charkose Jhadi (densely forest) in the north and located at entrance gate by
bus of Dharan Sub-metropolitan city. The average height of Campus area is 1148
ft (349m) above the mean sea level. Dharan has gently steep topography. The
area contains ground features ranging from step slopes to almost flat grounds.
For
conducting any type of work, we should know about the geology of that area.
Geology plays a vital role for the construction maintenance and rehabilitation
of any type of structure.
As
Dharan is underlain by Tertiary sediments (Siwalik) in the north and Quaternary
sediments (Terai Plain) in the south. For our concern, the Topographic survey
site falls in “Siwalik Zone” and Bridge site falls in “Terai Zone”.
1.4.3
Temperature, Climate and Vegetation:
According
to Central Bureau of Statistics, Dharan has a tropical monsoon climate with
maximum temperature of 35 to 36 Degree Celsius in April and minimum of 10 to 12
Degree Celsius in January.
Average temperature: 28˚C in summer
17˚C in
winter
Major Crops
grown: Paddy, wheat, maize etc.
Types of vegetation found: Herbs, Shrubs and tall trees, Peepal, Sirish,
Bamboo.
The temperature during the camp period was about 32˚C.
The days were hotter whereas in the evening, wind blew throughout the camp
period making the evening pleasant.
1.4.4
Others:
Dharan is one of beautiful cities of Nepal,
beautiful roads, remarkable homes and natural beauty. It embraces cleanliness,
openness, friendly hill people and their smiles. A famous hill station called
Bhedetar (19 KM from Dharan) lies in the north and it has remained the place of
relief for the people of Dharan during the summer as the heat begins to rise.
In the autumn when the sky becomes clear, one can witness the breathtaking
range of mountains. The distinct view of Makalu can be seen from this area. Many
fine lodges and the restaurants are now opened up for the tourists and the
people coming for the cool and fresh air. The tower named Charle’s tower
situated on the top of the hill is one of the exciting spots indeed from where
one who can see excellent views of Hile-Dhankuta, Kanchenjunga Himal in the
north and a really large valley with Sapta Koshi river along with Dharan Bazaar
very close but really down. Dharan grew after British setup the ‘Gurkha
Recruitment Center’ in 1953. Two ethnic groups namely Rais and Limbus used to
constitute the major portion of the Gurkha soldiers and these groups came from
the eastern region of Nepal for their training. Pindeshwar, Dantakali, Budha
Subba, Panchkanya Temples are all located in historically and archeologically
important Bijaypur hill. A famous Barahchatra temple at Chatara is very near to
Dharan. Koshi Tappu Wildlife Reserve is the only refuge for wild buffalo and is
home for more than 300 species of birds. Dharan is also the gateway for the
many north/east hill regions and starting point for the trekkers to the
Kanchenjunga, Solu Khumbu and the Arun Valley. Dharan enjoys many fine lodges
and the elegant restaurants which serves the good meals but is short of star
hotels. The shopping mall named Bhatbhateni and Gorkha Shopping Complex is also
at Dharan. Dharan is also remaining an educational center for the eastern
Nepal; boosts some of the fine colleges, schools and the medical college. B.P.
Koirala Institute of Health Science is not only a major medical institute of
Nepal but also serves high quality health care services to eastern Nepal and
north parts of India. Besides IOE/ Purwanchal Campus, Central Campus of
Technology (Food and Beverages Technology) Hatisar, Mahendra Multiple Campus
are constituent campuses of TU and Pindeswor Bidyapitha (Sanskrit) are the
major institution of Dharan.
CHAPTER:2
TOPOGRAPHICAL
SURVEY
Introduction
Topographic surveying is the process of determining the
positions, both on the plan and
elevation, of the natural and artificial features of a locality for the purpose
of delineating them by means of conventional signs upon a topographic map. Topography
defines the shape or configuration of the earth’s surface.
The basic purpose of a topographic map is to
indicate the three-dimensional relationships for the terrain of any given area of land. Thus, on a topographic map,
the relative positions of the
points are represented both horizontally as well as vertically.
2.1 Brief Description of the Area:
The area through which the major
traverse was run was a small portion of the whole IOE Purwanchal Campus
premises. Along with the preparation of the topographical map of the major
traverse, detailed topographical map of the small area with contours was also
prepared. The area on which detailed topographical survey was performed
includes: Administration, all departments, canteen, football ground and both
boys and girls hostels.
Fig: Traversing of
IOE Purwanchal campus
2.2 Objective
The
main objective of the topographic survey undertaken here is to prepare
the topographic map of the given IOE
Purwanchal campus, with horizontal as well as vertical controls within
pre-determined accuracy. Apart from this, some of
the other objectives are summed-up as follows:
Ø To use and become familiar with different kinds of surveying instruments.
Ø To select and use appropriate methods
to undertake the topographic survey.
Ø To fix Major traverse to cover the maximum area to be surveyed.
Ø To fix Minor traverse
for comfort and control in detailing.
2.3 Norms (Technical
Specifications)
1.
Reconnaissance survey
of the area to be surveyed.
Form a closed traverse (major
and minor) around the premises of the
area by fixing or marking
appropriate no. of stations (13-15). In the selection
of the traverse
stations the leg ratio, i.e. the
ratio of length of the longest traverse leg to the length of the smallest leg, should be less than or
equal to 1:2 for major traverse
and 1:3 for the minor traverse.
2. Two-way measurement of the traverse legs by means of a
Total Station. Accuracy of two way measurement in the case of major traverse is 1:5000 and minor traverse. (Two way measurement, i.e. measurement of the traverse
leg in the forward as well as in the backward direction.)
3.
Two sets of angle measurement making
use of a Total Station. Measure two sets of
horizontal circle reading of major traverse stations either by Total Station or Theodolite. The difference
between face left and face right readings should be within 30”. Note the
difference between the mean angles of two sets reading should be within 1’.
4.
Determination
of RL of traverse stations by fly leveling from the given BM.Perform two
peg test. Collimation error in the case of two peg test should be better than 1:10000. Balancing of back sight and fore sight is necessary
for the elimination of different
types of errors including collimation error. The permissible error of fly leveling is ± 25√K mm, where K is the distance of the leveling passed in kilometer.
5.
Adjustment of traverse or balancing the traverse.
The permissible angular error or the angular misclosure for the sum of interior angles of the traverse should be within C√N, where N denotes the no. of traverse leg or traverse stations
and, C=10’’ for major traverse and C=1’ for minor traverse.
For major traverse the relative error of closure should be less than 1:3000
and that for minor should be less than
1:2000.
6.
Plotting of the traverse
stations by co-ordinate method. An appropriate scale is
selected, i.e. 1:500 for the major
traverse and for the minor traverse.
7. Detailing or the detail survey of
the plot by Tachometric surveying.
References are drawn from the major and minor traverses. The details are extracted from a self-recording Total station. Conventional symbols are used to denote the detailing along with the contours of 0.5 m contour interval in the same scale in topographic survey and 1m
contour interval for road alignment and bridge survey.
2.4 Equipments
The equipments used for the topographic survey
are listed as follows
1. Total Station with tripod
2. Auto level with tripod
3. Compass with tripod
4. Staffs
5. Target prisms with stands
and leveling bubble provided
6. Ranging rods
7. Plumb bob
8. Tapes
9. Plane table
10. Alidade
11. Spirit level
12. Arrows
13. Hammer
14. Pegs
15. Enamel paints
and marker
2.5 Methodology
The different methodologies
were used in surveying to solve the problems arise in the field. These
methodologies are as follows:
2.5.1 Reconnaissance:
Reconnaissance (Recce) means the
preliminary inspection of the area before commencing the actual detail survey,
for the purpose of fixing the survey stations and forming a general plan for
the network of the chain lines. This helps to make the necessary observations
regarding the total area, type of land, topography, vegetation, climate,
geology and intervisibility conditions that helped in fetailed planning. For
this purpose the detailed inspection of the given area was carried out by
reconnaissance survey. During reconnaissance, the major and minor traverse
control points to form a closed traverse around the perimeter of the area was
found out.
While selecting the major and minor
control points, the following points should be considered:
Ø Location should
be such that the basic principle of surveying i.e. working from whole to the
part gets implemented.
Ø Number of stations should be minimum as far as
possible but the possible figures joining the stations should be well
conditioned.
Ø Length of the traverse lines better be as long as
possible to reduce the effect of centering error.
Ø The indivisibility among stations and at least between
adjoining stations is required.
Ø Stations should be positioned on firm and level
ground.
Ø While selection of stations the leg ratio should be
maintained its consecutive legs and in overall leg distance 1:2 or 1:3.
2.5.2 Traversing
Traversing
is the type of surveying in which a number of connected survey lines form the
frame work, which is used for housing, factory sides, determination of
perimeter of lakes, setting out and detailing of many engineering works. The
main purpose of traversing is to find control points. When there is large
extend of chaining triangulation, generally traversing is used. It is the
method of control survey. The survey consists of the measurement of angle
between the successive lines or bearing of each line and the length of each
line. These are done with the help of angle measuring instrument, theodolite or
tape. If the coordinate of first station and bearing of first line are known,
then the coordinates of all successive points can be computed. Traversing is of
two types:
(a)
Open
Traverse
A traverse is said to be open traverse when the
traverse starts at one point and terminates at another point as shown in the
figure. Open traverse is also called as unclosed traverse. It is suitable for
surveying of roads, coastal lines, etc
.
Fig1:open traverse
(b) Close Traverse
A traverse is said to be closed
traverse when the traverse formed a closed circuit as shown in the figure. In
this case, both starting and terminating points of the traverse coincide with
each other. It is suitable for the survey of boundaries of ponds, sports
grounds, forests, etc. It is further divided into two types: Closed loop closed
traverse and open loop closed traverse (Link traverse).
Fig 2 : Closed Traverse
2.5.2.1 Major Traverse
The
skeleton of lines joining those control points, which covers the whole entire
area, is called Major Traverse. Two-set of readings are taken for Major
Traverse as the work done on major traverse need to be precise. For
convenience, the readings are taken by setting the total station at 00˚00’00”
for one set and 90˚00’00” for another.
The major traverse had 13 control stations including two
given control points. The control stations were named as H1, H2, ….,H11 and two
control points as CP1 and CP2 respectively. The leg ratio of maximum traverse
leg to minimum traverse leg was maintained within 2:1. The precision in length
between the forward measurements and the backward measurements of all the
traverse legs was within 1:5000 when measured through total station. The
difference between the mean angles of two sets of readings was within a minute
for all the angles whereas for two face reading was within 30’’ for all the
measured angles.
Computation of
Co-ordinates:
The
length of the traverse is measured by total station. The traverse angles are
measured with a total station by setting up the instrument at each station. The
bearing of the any one of the traverse leg measured and the entire traverse
angle measured, the bearing of all the legs can be calculated by:
Bearing
of a line = (bearing of previous line + included angle) ± (180˚ ) or (540˚)
If
θ is the bearing of line (C.P, A say), and l be the length of the line and
provided that co-ordinate of the control point (C.P) is known then the coordinate
of the point ‘A’ can be calculated as follows:
Independent X-coordinate of A =
x-coordinate of control point (c.p) +L*sinθ
Independent Y-coordinate of A =
y-coordinate of control point (c.p) + L*cosθ
Where, L* sinθ and L*cosθ denote the consective coordinates of
the line
R.L or z-coordinate of A = R.L of
point (c.p) + H.I ± V - Height of signal
Where, H.I = Height of instrument V =
Vertical distance
Closing Error
|
In
a closed traverse, the algebraic sum of the latitudes and departures must be
zero if linear as well as angular
measurements of the traverse along with their computations are correct. If not, the distance between
the starting station & point or position of the same station obtained by the calculation is known as closing error.
The value of closing error is obtained
by the following formula.
|
|
|
Error=
Fig:Closing Error
2.5.2.2 Minor traverse:
For
the detailed topographical survey, the detail points may not be sufficiently
obtained from the control stations of the major traverse. For this minor
traverse need to be laid. Minor traverse is that one which runs through the
area to make detailing easy. Minor Traverse covers only small area. Less
precise work than that of major traverse is acceptable so that single set
reading is sufficient. The minor traverse had 6 control stations. The stations
were named as h1, h2…., h6. The leg ratio of maximum traverse leg to minimum
traverse leg was maintained within 3:1. The precision in length between
the forward measurements and the backward measurements of all the traverse legs
was within 1:2000.
2.5.2.3 Balancing the traverse
The process of adjusting the consecutive co-ordinates by applying the correction to the
latitudes & departures of each of the traverse legs such that their
algebraic sum is equal to zero is called balancing
the traverse or balancing the consecutive co- ordinates.
A closed traverse
can be balanced by any one
of the following methods.
i.
Bowditch’s method
ii.
Transit rule
iii.
Graphical method
iv.
Axis method
i.
Bowditch’s Method
The method is based on the assumption that errors in the
linear measurement are proportional to √L and the errors in the angular measurements are inversely proportional to √L where ‘L’ is the length
of a line. The method is applicable when both the linear as well as angular measurements are of equal precision.
The Bowditch rule is:
Correction to latitude
(or departure) of any side=
=Total error in
latitude or departure x
Where, CLat =
Correction to latitude of that side
CDep = Correction to
departure of that side
ΣLat = Total error in latitude
ΣDep = Total error
in departure
ΣL = Total
perimeter of traverse
L = Length of that side
ii. Transit Method
The method is most
applicable when angular measurements are of more precision than linear
measurement. According to this rule, the total error in latitude and in departure
is distributed in proportion to the latitude and departure of the sides. The
angles are less affected by the corrections applied by this method than by the
Bowditch method.
The Transit
rule is:
Correction in Latitude (or Departure) of any side
= 𝑇𝑜𝑡𝑎𝑙 𝐸𝑟𝑟𝑜𝑟 𝑖𝑛 𝐿𝑎𝑡𝑖𝑡𝑢𝑑𝑒 𝑜𝑟 𝐷𝑒𝑝𝑎𝑟𝑡𝑢𝑟𝑒 x
CL=ΣL* CD=ΣD*
Where, CL= Correction to latitude of any side
CD = Correction to departure of any side
L = Latitude of any line
D = Departure of any line
LT =
Arithmetic sum of latitudes
DT = Arithmetic sum of departures
2.5.3 Detailing
Detailing
means locating and plotting relief in a topographic map. Detailing can be done
by either plane table surveying or tachometric surveying or by total station.
We performed detailing by total station, detailing by tachometry and tangential
method while taking details during the camp.
Total Station
A total station is an
electronic/optical instrument in modern surveying and building construction
that uses electronic transit theodolite in conjunction with electronic distance
meter (EDM). It is also integrated with microprocessor, electronic data
collector and storage system.
Fig 3: Total Station and its parts
The instrument is used to measure
sloping distance of object to the instrument, horizontal angles and vertical
angles. This Microprocessor unit enables for computation of data collected to
further calculate the horizontal distance, coordinates of a point and reduced
level of point. Data collected from total station can be downloaded into
computer/laptops for further processing of information. Total stations are
mainly used by land surveyors and civil engineers, either to record features as
in topographic surveying or to set out features (such as roads, houses or
boundaries). They are also used by archaeologists to record excavations and by
police, crime scene investigators, private accident Reconstructionist and
insurance companies to take measurements of scenes.
Types of Total Station
Usually, these three types are used
in the total stations given in the chart and their operations.
Types |
Vertical Angle |
Horizontal Angle |
Slope distance |
Manual |
manually |
manually |
electronically |
Semi-automatic |
digitally |
manually |
electronically |
Automatic |
electronically |
electronically |
Co-ordinate
system |
Besides, there are many other types
of total stations as well. The total handheld station is the most popular form
which uses an internal or external antenna for photogrammetric processing. The
mobile total station gives us mobility attached to a motorized platform. The
fixed station provides services from a stationary point. Scanning Total
Stations, Robotic Total Stations, autolock Total Stations, prism total
stations, and Total Mechanical Stationary are also kinds of total stations.
I.
Tacheometry:
It is the branch of surveying in which both
the horizontal and vertical distances between stations are determined by making
instrumental observations. Tacheometry is used in the preparation of contour
maps and they also provides a good check on distances measured with tape or
chain.
Principle of tacheometry:
In isosceles triangles, the ratio of
the perpendiculars from the vertex on their bases is constant.
The formula for the horizontal distance is
H=k∗s Cos2𝜃
The formula for the vertical distance is
V = (k∗s Sin2θ)/2 )
Where, s = staff intercept ;
θ
= Vertical Angle
Thus knowing the value of V,
reduced level (R.L.) of instrument station, Height of instrument (H.I.)
and central wire reading (R), the R.L. of any point under observation
can be calculated as:
R.L.of point = R.L. of
instrument station + H.I. ± V - R
II.
Detailing by trigonometric leveling:
In this method we have to
take two middle staff reading, with 2 different vert. angle along with
horizontal angle with any traverse leg.
We use the formula:
S=difference in staff reading
H=S / (tan(90-θ1)-tan(90-θ2))
V=H tan(90- θ2)
where,θ1 is smaller zenithal angle and θ2 is bigger zenithal angle.
2.5.4
Levelling
Leveling is an art of determining
relative altitudes of points on the surface of the earth or beneath the surface
of the earth. It is used to find the elevation of given points with respect to
a given or assumed datum and to establish points at a given elevation or at
different elevations with respect to a given or assumed datum. Leveling deals
with measurements in a vertical plane. Finding out elevation is necessary to
enable the work and establishing points are necessary in the setting out of
works. The different methods of leveling are explained as follows:
a) Simple Leveling:
The operation
of leveling for determining the difference in elevation, if not too great,
between two points visible from a single position of the level, is known as
simple leveling.
b) Differential Leveling:
The method of
leveling for determining the difference in elevation of two points either too
far or obstructed by an intervening ground, is known as differential leveling.
The level is set up at number of points and the difference in elevation of
successive points, is determined in this method.
c) Check Leveling:
After the
completion of fly leveling, level lines are run to check the accuracy of the
bench marks previously fixed which is called check leveling.
d) Profile Leveling:
The operation
of leveling carried out to determine the elevations of the points at known
distances apart, and also salient features, along a given straight line is
called profile leveling. It is also known as longitudinal leveling.
e) Cross-section leveling:
The
operation of leveling which is carried out to provide levels on either side of
the main line at right angles, in order to determine the vertical section of
the earth surface on the ground is called cross section leveling.
f) Reciprocal leveling:
When the level
is not possible to be set up between two points due to an intervening
obstruction as large water bodies, reciprocal leveling is carried out. The two
sets of reciprocal leveling is done to find out the difference in elevation
between two points accurately.
Temporary adjustments of
Level:
The temporary adjustments for
a level consist of the following:
a) Setting up the level:
The
operation of setting up includes fixing the instrument on the stand and
leveling the instrument approximately.
b) Leveling up:
Accurate
leveling is done with the help of foot screws and with reference to the plate
levels. The purpose of leveling is to make the vertical axis truly vertical and
horizontal line of sight truly horizontal. It is done by adjusting the screws.
c) Removal of parallax
Parallax is
a condition when the image formed by the objective is not in the plane of the
cross hairs. Parallax is eliminated by focusing the eye-piece for distinct
vision of the cross hairs and by focusing the objective to bring the image of
the object in the plane of cross hairs.
2.5.5 Permanent adjustments of Level (Two peg test):
To check for the collimation error of level two-peg
test should be performed. Two staffs were placed at A and B of known length.
First the instrument was setup on the middle point of A and B and staff
readings (Top, Middle and Bottom) on A and B were taken. Second the instrument
was setup behind A and again staff readings were taken on A and B. The was done
in order to check whether the adjustment was within the required accuracy or
not. The error obtained was within the given permissible error. So, the
permanent adjustment was not required.
Fig :Two-peg
test
Booking of reducing levels:
There
are two methods of booking and reducing the elevation of points from the
observed staff reading:
1.
Height of
the Instrument method
Arithmetic Check: B.S. – F.S. = Last R.L. – First R.L.
2.
Rise and
Fall method
Arithmetic Check: B.S. – F.S. = Rise –Fall =
Last R.L. – First R.L.
Among
the two methods, Rise and Fall method was widely used.
Fly Leveling:
The fly leveling was carried out between TBM 2 and TBM 3
and check leveling was performed to check the results.
Level transfer to the major and minor traverse stations:
The R. L of the temporary benchmark was then transferred
to the control stations of the major and minor traverse. The closing error was
found to be within the permissible limits. The misclosure was adjusted in each
leg of the leveling path by using the following formula:
Permissible error = ±25√k mm.
Where k is the total perimeter in Km
Actual Error (e) = ∑BS – ∑F.S. = Last R.L. – First R.L.
Correction i th leg=-(e * (L1 + L2 +…. + Li)/P
Where L1, L2, Li Length of 1st 2nd, …... i
th leg and P is perimeter. Relative Precision= 1/(p/e)
2.5.6
Contouring
A contour is an imaginary line of
constant elevation on the ground surface. It is the line in which the
surface of the ground is intersected by the level surface.
2.5.6.1Contour interval
and Horizontal Equivalent
The vertical distance between any
two consecutive contours is called the contour
interval. The contour interval is kept constant for a contour plan or
the topographic map; otherwise the
general appearance of the map will be misleading. The horizontal distance between two points on two
consecutive contours is known as horizontal equivalent
and it depends upon the steepness of the ground. The choice of the proper contour
interval depends upon the following
considerations:
Ø The nature of the ground
Ø The scale of the map
Ø The purpose and the extent of the survey
Ø Time and expense of field and the office work
2.5.6.2Characteristics of Contours
The characteristic features of the
contour which are used while plotting and reading a contour map or the topographic map are summed up as follows:
1. Two contour
lines of different elevations cannot cross each other. They can cross each other only in the case of overhanging cliff.
2. Two contour
lines of different elevations cannot unite to form a single. If they do, it is
only in the case of vertical
cliff.
3. Closely
spaced contour lines represent a steep slope. BCanally spaced contour lines represent a gentle slope. Equally spaced
contour lines represent a uniform slope. A
series of straight, parallel and equally space
contours represent a plane surface.
4. A contour line cannot
split into two or more contour
lines.
5. A series of
closed contour lines with higher value of contour i.e. with contour having higher value of elevation inside
represent a hill where as a series of closed
contour lines with lower value of contour inside represent a pond or the
depressed land.
6. A contour
line must close upon itself, though not necessary within the limits of the map.
7. Contour
lines cross a watershed or the ridge line at right angles. They form curves of U-shaped round it with the
concave side of the curve towards the higher ground.
8. Contour
lines cross a valley line at right angles. They form sharp curves of V- shaped across it with the convex side of
the curve towards the higher ground.
9. The same
contour appears on the either side of a ridge or valley, for the highest horizontal plane that intersects the ridge
line must cut it on the both the sides. The same is true of the lower horizontal plane that cuts a valley.
4.5.5.2
Methods of Locating Contours
The location of a point in
topographic survey involves both horizontal as well as vertical control. The methods of locating contours,
therefore, depend upon the instruments used.
a. The direct method
b. The indirect method
In the direct method, the contour to be plotted is actually traced on the
ground. Only those points are
surveyed which needs to be plotted. After having surveyed those points, they are plotted and the contours
are drawn through them. The method is slow and
tedious and is used for the small
areas where great accuracy is required.
In the indirect method, some suitable guide points are selected and
surveyed; the guide points need not
necessarily be on the contours. These guide points, having been plotted, serve as basis for the
interpolation of contours. This is the method most commonly used in engineering surveys.
4.5.5.3 Interpolation of the Contour lines
Interpolation of the contour is
the process of spacing the contours proportionately between the plotted ground points established by indirect
methods. The method of interpolation
is based on the assumption that the slope of the ground between the two points, which are surveyed, is uniform.
There are different methods of interpolation of contours. They are as follows:
i) Estimation
ii) Arithmetic calculations
iii) Graphical method
iv) Estimation
This method is extremely rough and is used for small scale work only. The position of the
contour points between the guides
points are located by estimation.
i.
Arithmetic Calculations
The method, though accurate, is time consuming. The position of contour points
between the guides points are located by arithmetic
calculation.
Where, X= Horizontal distance of the point
to be located H= Horizontal distance between two guide points
V= Vertical distance
between two guide points
Y= Vertical distance
between the point to be located and lower elevation point
ii.
Graphical Method
In the graphical method, the
interpolation is done with the help of a tracing paper or a tracing
cloth.
2.6 Comments and Conclusion:
The site for the survey camp was suitable for
us to practice the theoretically acquired knowledge in the field. Laying
control stations, carrying out level works and angular measurement became
difficult while laying stations on bushes side. The obstructions due to trees
created problem. The work was slowed down as some of the instruments provided
were with errors. Also, during fly leveling from TBM1 to cp1, we faced
difficulties due to traffic disturbances. However, the given topography survey
camp was finished within the given span of time. The subject survey needs
practice as much as possible. For surveying, theory can only take as the
introduction but if there is practice, there will be much gain of knowledge
about the techniques of surveying. Thus, this camp helps us by practicing the
survey work to gain the much essential knowledge as far as possible. It is
better to say that it provides us a confidence to perform survey and apply the
techniques at any type of problem facing during the actual work in the future
career.
CHAPTER:3
BRIDGE SITE SURVEY
Bridges are the
structures that are constructed with the purpose of connecting two places
separated by deep valleys or gorges or rivers and streams. Bridges are usually
the cross drainage and hence a part of roads making them shorter and hence
economical. In countries like Nepal, where there are a lot of uneven lands and
plenty of rivers. Thus, bridges are the most economic and efficient way to join
two places by road in a very convenient way.
3.1 Objectives:
The main objective of the bridge site survey is to give
the students the preliminary knowledge on selection and planning of possible
bridge site and axis for the future construction of the bridge. The purposes of
the bridge site survey are:
Ø
To select the possible bridge site and axis for
the construction of bridge.
Ø
To collect the preliminary data i.e. normal
water flow level, high flood level.
Ø
To study about the geological features of the
ground.
Ø
To carry out surveying for topographical
mapping, longitudinal and cross sections at both upstream and downstream sides
of the river.
3.2 Brief description of the site:
Bridge site survey
was conducted over Sardu Khola. The Khola being seasonal, there is no water
during the survey time but highflood level extends to larger width. The bridge
site was surrounded by trees and bushes. The ground was sandy with numerous
boulders and rocks. The hill slopes on both sides were very steep and are thus
geologically unstable. Below axis of bridge, there is landslide prone area
where old traces of landslide are visible.
Hydrology, Geology & Soil:
The site is surrounded with
steep hill, which is covered with densely planted shrubs. The soil was sandy as
the basin is the fan base of river. The width of stream is not so big but high
flood level covers large area. Water scoured marks on the sideshow that the
highest flood level is quite high sometimes.
Technical Specifications (Norms):
The following norms were
followed while performing the bridge site survey in the field:
Ø
Carry out reconnaissance survey of the bridge
site area. Establish necessary triangulation stations to determine Bridge Axis
length, as well as horizontal and vertical control of the area. Well condition
triangles should be formed while selecting the triangulation stations
Ø
Control point fixing as well as determining the
length of the bridge axis had to be done by the method of triangulation. While
forming triangles, proper care had to be taken such that the triangles were
well conditioned, i.e. none of the angles of the triangle were greater than
120° or less than 30°.
Ø
Maintain free board distance at least 4m in
between invert of proposed bridge and high flood level mark.
Ø
In triangulation, distance of Base Line must be
measured in an accuracy of 1:2000.
Ø
Observe two sets of horizontal circle reading by
the theodolite to measure the angle of triangles. Note that the difference
between the mean angles of two sets of readings had to be within a minute.
Angular misclosure for base triangle should be ±30"N.
Ø
Compute the length of proposed bridge axis by
triangulation survey from two adjacent base triangles by using sine law and
determine the length of bridge axis by taking average length.
Ø
Conduct fly leveling to transfer the R.L. from
given B.M. to the nearest triangulation station of the bridge axis and make
circuit close for checking error of closure
Ø
Carry out reciprocal leveling to transfer level
from one bank to other bank of the river within a precision of ±24 k mm.
Determine the RL of the other triangulation stations by fly leveling from the
end point of bridge axis.
Ø
Plot a topographic map indicating contour lines
at suitable interval (contour interval = 1m). The scale for plotting the
topographical map had to be 1:500.
Ø
In order to plot the longitudinal section of the
river, data had to be taken along the riverbed 300 m upstream and at least 200
m downstream. Draw cross section at 20m interval from topographic map and one
at the bridge axis. The plot for the longitudinal section along the flow line
had to be done in a scale of 1:500 for vertical and 1:500 for horizontal, for
cross-section V=H=1:200.
3.3 Equipment
& Accessories:
The equipment used in the survey
during the preparation of topographic map in bridge site are as follows:
Ø
Total station
Ø
Theodolite
Ø
Leveling staffs
Ø
Ranging rods
Ø
Measuring tapes
Ø
Tripod stand
Ø
Hammer
Ø
Plumb bob
Ø
Nails and pegs
Ø
Marking pen
Ø
Compass
Ø
Prism
Ø
Prism holder
3.4 Methodology:
The various methods performed during the
bridge site survey were site selection, triangulation, leveling (fly leveling
and reciprocal leveling), detailing by total station, cross section, and L
section. The brief descriptions of these methodologies are given below:
3.6.1 Site Selection:
Site selection is the first and
foremost step for the construction of bridge. Several governing factors are
there for the site selection of the bridge. Geological condition,
socio-economic and ecological aspect etc. guides the way of selection of bridge
site. Therefore, the site was chosen such that it is laid on the very stable
rocks at the bed of river as far as possible and not affect the ecological
balance of the flora and fauna of the site area. The location of the bridge was
selected in such a way that the heights of the roads joined by the proposed
bridge were almost the same. This prevented a lot of cutting and filling to
maintain a gentle gradient. The bridge site was chosen in such a way that the
bridge axis was perpendicular to the flow direction and was also shorter in
span so as to make the construction economical. The starting point of bridge
axis was not laid on the curve of the road.
Triangulation
Triangulation
was performed for the determination of the approximate span of the bridge axis. The triangulation stations can be
taken as the control points for detailing. Two points on either bank of the
river were fixed as control points and one of the sides of the triangle was
taken as the bridge axis. The two triangles from each bank were fixed.
Fig : Triangulation network
The base line was measured accurately by two way taping as
well as tachometry and interior angles were measured by taking two sets of
reading by theodolite. The accurate span of bridge was computed by applying
sine rule. To minimize the plotting error well-conditioned triangles were
constructed i.e. the angles greater than 30 degrees, less than 120 degrees and
nearer to 60 degrees. The best triangle is equilateral triangle.
3.6.2 Topographic Survey:
For the topographic
survey of bridge site, triangulation was done. Triangulation is the process of
measuring the angles of a chain or a network. The main purpose of the
triangulation was to determine the length of the bridge axis. The triangulation
also serves the control points for detailing. The bridge axis was set and
horizontal control stations were fixed on either side. Distances between
stations on the same sides of river i.e. base lines were measured with tape
precisely. Then the interconnecting triangles were formed and angles were
measured with the theodolite with two sets of observations. The bridge axis
length or span was calculated by solving the triangles using the sine rule. For
vertical control, the level was transferred from the arbitrary benchmark and RL
was transferred to the stations on the next bank by reciprocal leveling while
direct level transfer method was used or the same bank.
3.6.3 L-Section & Cross Section:
For gaining an idea about bed slope, nature of the
riverbed, and the variation in the elevations of the different points along the
length of the river, L-section is carried out. Keeping the instrument at the
control (traverse) stations on the river banks, the staff readings were taken
at different points along the center line of the river up to 150 meters upstream
and 50 m downstream. The RLs of the traverse stations being known previously,
the levels of the different points on the river were calculated. Then the
L-Section of the riverbed was plotted on a graph paper on scale for vertical
and horizontal.
Cross-section of a river at a particular point is the
profile of the lateral sides from the centerline of the river cut transverse to
the L-Section at that point. The cross section can be used to calculate the
volume and discharge of water at the particular section if the velocity at the
cross section is known. Cross sections were taken at an interval of about 20 m
extending 300 m upstream and 200 m downstream of the river. Staff readings of
points along a line perpendicular to the flow of river were taken from the
stations points and the elevations of the points were calculated using
tachometric methods.
3.6.4 Leveling:
Transferring R.L. from B.M. to control points: The R.L. of
benchmark TBM was given and was transferred to the triangular station from the B.M.
by fly leveling by taking the back sight-reading to the bench mark which should
be within the given accuracy. The R.L. was transferred to the opposite bank of
the river by reciprocal leveling.
Reciprocal Leveling:
This method is applicable when taping is obstructed but
not the vision. For transferring the RL across the bridge reciprocal leveling
was performed. This method eliminates the error due to focusing, collimation,
earth’s curvature and refraction of atmosphere etc.
True difference in elevation
between A and B = H = ha- (hb-e)
Also the true difference in elevation = H = (ha'-
e) – hb'
Fig:Reciprocal Levelling
Taking the average of the two
differences we get the difference in elevation between A and B i.e.
3.6.5 Detailing:
Total station was used for
detailing of the entire bridge site. The reading was taken from the different
station set up. The detailing was done with respect to the skeleton formed by
triangulation. The vertices of triangles serve as a control point. The details
were booked, up to 150m upstream and 50m downstream. The data and the
calculations have been tabulated in a systematic way.
3.6.6 Computation & Plotting:
The use of total station makes
the detailing process easy and fast. The total station gives the direct vales
of the horizontal distances and vertical height difference between the station
point and the detailing point. The RLs of the points can be calculated by using
following formula.
RL of detail = RL of
station + HI ± V-Target Height
The following tacheometric
formulae were used for the calculation of the horizontal distance and R.L. of
different points:
Horizontal distance of any point
from the traverse station,
H = 100 * S * cos2θ
where, S = Staff intercept
θ = Vertical angle
And R.L. of any required point is
R.L. = R.L. of station +
HI + H*tanθ - Mid wire reading
The topographic map, the longitudinal
section and the cross section were plotted on the respective scales after the
completion of calculations. By taking an A1 grid sheet, control stations were
plotted accurately. Then all hard details as well as contours were plotted with
reference to the control stations by the method of angle and distances.
3.7 Comments and Conclusion:
As a civil engineer, we should
design the bridge with the view point of economic and its durability. The
bridge axis should be designed such that the span length should be minimum and
the location is safe. The bridge axis should not be below the highest flood
level. No springs and streams are added in the river to the surveyed area.
Also, the drainage and sewage have been discharged into the river. The
cross-section was taken at middle of the river to get the profile of the
flowing river. Also, we marked the high flood level.
CHAPTER:4
ROAD ALIGNMENT
A road is an identifiable route,
way or path between two or more places. Roads are typically smoothed, paved, or
otherwise prepared to allow easy travel; though they need not be, and
historically many roads were simply recognizable routes without any formal
construction or maintenance. The road needs to pass through positive obligatory
points. Positive obligatory points include cities, schools, markets and
negative obligatory points include temples, national parks and wild life
conservation areas. Road must not pass through such negative obligatory points.
Before the construction of the road,
preliminary survey is done. Road alignment is the preliminary stage of road
construction. Selection of Intersection Points (IP) is the foundation of
construction of the road. After that cross section, longitudinal section and formation
level are required.
4.1 Objectives
The main objectives of the road
survey are as follows:
Ø To
design the alignment of road in the actual field by fixing IPs.
Ø To
take the details of the land features of the surrounding area of the planned
road.
Ø To
prepare the Longitudinal section and cross section of the road at certain
required chainage so that nature of terrain can truly represented in graphs.
Ø To
calculate the amount of cutting and filling and estimate the cost of work.
4.2 Brief description of the project area:
Road alignment survey is conducted on the
river on which bridge is proposed. As, we are concerned about taking skills and
knowledge, the terrain of river provides a lot of undulation. This specific job
is essential for an engineer combating with the mountainous topography of
Nepal. Road alignment survey was conducted assuming the axis of the bridge as
initial ip.
Geology, Hydrology & Soil:
The road had to go along a route of stream
that was much undulated. There were number of large boulders or rocks of any
kind along the proposed site. The soil is uniform throughout the whole length
of the road. The road alignment has certain up and downs. Because of gentle
slope, the vertical curve was not required. Sandy soil was found along the road
course.
Technical Specifications (Norms):
Reconnaissance of alignment selection was
carried out of the road corridor considering permissible gradient, obligatory
points, bridge site and geometry of tentative horizontal and vertical curves.
The road setting horizontal curve, cross sectional detail in 20m interval and
longitudinal profile were prepared.
The topographic map (scale 1:500)
of road corridor was prepared. Geometric curves, crossings and other details
were shown in the map.
While performing the road alignment survey, the following
norms were strictly followed:
Ø Carry
out reconnaissance survey and alignment selection of a road corridor about 700m
or more.
Ø If
the external deflection angle at the I.P. of the road is less than 3°, curves
need not be fitted.
Ø Simple
horizontal curves had to be laid out where the road changed its direction,
determining and pegging three points on the curve - the beginning of the curve,
the middle point of the curve and the end of the curve along the centerline of
the road.
Ø The
radius of the curve had to be chosen such that it was convenient and safe. The
radius of the curve should not be less than 15m. The radius must be within the
multiple of 5 or 10.
Ø Point
of commencement (T1) and point of tangency (T2) must not be located within the
bridge axis. Start and finish of curves must be totally outside the bridge axis
end points.
Ø Subsequent
reverse as well as compound curves in road alignment should be avoided.
Ø The
deflection angle should not be greater than 90˚.
Ø Two
successive curves must not be overlapped.
Ø Carry
out leveling survey for longitudinal section along the centre line at 20m
interval, at abrupt change point and at all the curve point BC, MC and EC.
Close the leveling survey and check the RL at job site immediately. Permissible
error of closure for leveling must not be greater than ±25 √k mm.
Ø Cross
sections had to be taken at 15 m intervals and at the beginning, middle and end
of the curve, along the centerline of the road - observations being taken for
at least 10 m on either side of the centerline.
Ø Plan
of the road had to be prepared on a scale of 1:500.
Ø L-Section
of the road had to be plotted on a scale of 1:1000 horizontally and 1:100
vertically.
Ø The
cross section of the road had to be plotted on a scale of 1:100 (both vertical
and horizontal). The amount of cutting and filling required for the road
construction had to be determined from the L-Section and the cross sections.
However, the volume of cutting had to be roughly equal to the volume of
filling.
Equipment & Accessories:
The following are the instruments
used during the road alignment survey in the field:
·
Total station
·
Theodolite
·
Leveling staffs (5m)
·
Ranging rods
·
Measuring tapes (30m and 5m)
·
Leveling instrument
·
Tripod stand
·
Nails and pegs
·
Marking pen
·
Plumb bob
·
Arrows
4.6 Methodology:
The alignment of road includes several ways and procedures
that need to be carried out. Following are the listed methodology:
4.6.1 Reconnaissance:
The reconnaissance survey was performed along the given
route. Tentative estimation was done for the intersection points, where the
direction had to be changed. While returning back the route, the IPs was fixed.
For this the inter-visibility of the stations was checked. Meanwhile the pegs
with IP no. were driven at these points.
4.6.2 Horizontal Alignment:
Horizontal
alignment is done for fixing the road direction in horizontal plane. For this,
the bearing of initial line connecting two initial stations was measured using
compass. The interior angles were observed using theodolite at each IP and then
deflection angles were calculated.
Deflection
angle = 180˚- observed angle
If the deflection angle is positive the deflection is
towards right and if the deflection angle is negative the deflection is towards
the left. The radius was assumed according to the deflection angle. Then the
tangent length, Beginning of the Curve (BC), End of the Curve (EC), apex
distance along with their chainage were found by using the following formulae,
Tangent length (T) = R*tan(∆/2)
Length of curve (L.C) = Π * R * ∆
/180
Apex distance = R *(sec( ∆/2)-1)
Chainage of BC = Chainage of IP – T
Chainage of MC = Chainage of BC
+LC/2
Chainage of EC = Chainage of MC +
LC/2 = Chainage of BC + LC
The BC and EC points were located
along the line by measuring the tangent length from the apex and the points
were marked distinctly. The radius was chosen such that the tangent does not
overlap. The apex was fixed at the length of apex distance from IP along the
line bisecting the interior angle.
4.6.3 Vertical Alignment:
Vertical profile of the Road
alignment is known by the vertical alignment. In the L-section of the Road
alignment, vertical alignment was plotted. According to Nepal Road Standard,
Gradient of the Road cannot be taken more than 12 %. In the vertical alignment,
we set the vertical curve with proper design. Vertical curve may be either
summit curve or valley curve. While setting the vertical alignment, it should
keep in mind whether cutting and filling were balanced or not.
4.6.4 Leveling:
The method of
fly leveling was applied in transferring the level from the given B.M. to all
the I.Ps, beginnings, mid points and ends of the curves as well as to the
points along the center line of the road where the cross sections were taken.
After completing the work of one-way fly leveling on the entire length of the
road, check leveling was continued back to the B.M. making a closed loop for
check and adjustment. The difference in the R.L. of the B.M. before and after
forming the loops should be less than 25√ k mm, where k is the loop distance in
km.
4.6.5 L-section & Cross Section:
Nature of the
ground, the variation in the elevations of the different points along the
length of road need to be known for the construction of the road. For this
L-Section of the road is required. In order to obtain the data for L-Section,
staff readings were taken at points at 20m intervals along the centerline of
the road with the help of a level by the method of fly leveling. Thus, after
performing the necessary calculations, the level was transferred to all those
points with respect to the R.L. of the given B.M. Then finally the L-Section of
the road was plotted on a graph paper on a vertical scale of 1:100 and a
horizontal scale of 1:1000. The staff readings at BC, EC and apex were
also taken. The RL of each point was calculated.
Cross sections at different points
are drawn perpendicular to the longitudinal section of the road on either side
of its centerline in order to present the lateral outline of the ground. Cross
sections are also equally useful in determining the amount of cut and fill
required for the road construction. Cross sections were taken at 20m intervals
along the centerline of the road and at points where there was a sharp change
in the elevation. While doing so, the horizontal distances of the different
points from the centerline were measured with the help of a tape and the
vertical heights with a measuring staff. The R.L. was transferred to all the
points by performing the necessary calculations and finally, the cross sections
at different sections were plotted on a graph paper on a scale of both
vertical and 1:100 – horizontal.
Curve Setting:
A regular curved path followed by
highway or railway alignment is curve. It is introduced wherever it is
necessary to change the direction of motion due to the nature of terrain. A
curve may be circular, parabola or spiral and is always tangential to two
straight directions.
There may be different types of
curves:
Simple curve, Compound curve, Reverse curve, Transition curve.
Simple Circular Curve:
A simple circular curve is the curve, which
consists of a single arc of a circle. It is tangential to both the straight
lines.
Setting Out of Simple Circular
Curves:
1. Linear method: - In this method,
only a chain or tape is used. Linear methods are used when a high degree of
accuracy is not required and the curve is short.
E.g: Offsets from Long Chord
Offsets form Tangents
Successive bisection of Chords
Offsets from Chords produced
2.Angular method: - In this method,
an instrument like theodolite is used with or without chain or tape. E.g.:
Rankine’s Method of Tangential Deflection Angles,Two Theodolite Method
Offset from Long Cord Method:
Mid-ordinate can be determined by
the relation
Oo = R - [R2 – (L/2)2] T
he Ordinate at a distance ‘x’ is
given by,
Ox = [ ( R2 – X2) – ( R - Oo ) ]
Where, Oo = mid-ordinate
Ox = ordinate at distance x from
the mid point of the chord
L = length of the long chord
R = Radius of the curve
Rankine’s Method:
In Rankine’s
method, it’s assumed that the length of the curve and the chord length are
equal (case for larger radius). The deflection angle to any point on the curve
is an angle at the point of contact between the back tangent and the chord
joining the point of contact and that point.
Here:
∠T1Oa
= 2 δ1
Chord T1a~ Arc
T1a
∠T1Oa
/ l1 = 360◦/(2πR)
2δ1 = 360◦/ (2π
R)
δ1 = (360◦× l1)
/ (2 × 2πR) degrees
δ1 = (360◦×60× l1)
/ (2 × 2πR) minutes
δ1 = (1718.9 ×
l1) / R minutes
Similarly, δ2 =
(1718.9 × l2) /R minutes
δ3 = (1718.9 × /R minutes and
so on.
Finally: δn =
(1718.9 × ln) /R minutes
Also, ∆a=
δ1
∆b= δ1 + δ2
∆c= δ1 + δ2 + δ3 and so on.
∆n= δ1 + δ2 + δ3 … …
… + δn
Arithmetical check: ∆n=
∆/𝟐
Field Procedure:
a.
Locate the tangent points (T1 and T2) and find out
their changes. From these changes, calculate the lengths of first and last
sub-chords and the total deflection angles for all points on the curve as
described above.
b.
Set up and level the theodolite at the first tangent
point (T1).
c.
Set the vernier A of the horizontal circle to zero and
direct the telescope to the ranging rod at the intersection point B and bisect
it.
d.
Loosen the vernier plate and set the vernier A to the
first deflection angle Δ1, the telescope is thus directed along T1D. Then along
this line, measure T1D equal in length to the first sub-chord, thus fixing the
first point D on the curve.
e.
Loosen the upper clamp and set the vernier A to the
second deflection angle Δ2, the line of sight is now directed along T1E. Hold
the zero end of the chain at D and swing the other end until the arrow held at
that end is bisected by the line of sight, thus fixing the second point (E) on
the curve.
f.
Continue the process until the end of the curve is
reached. The end point thus located must coincide with the previously located
point (T2).
4.8 Comments and Conclusion:
Survey
of the road alignment is done to make safe, easy, short and economical road.
Geological stability and soil stability are also taken into account. Vertical
and horizontal curves are set according to Road Design Standards for comfort
and other factors. While setting the road alignment, it should be kept in mind
that the minimum IP points should be taken as far as possible and deflection
angles should be minimal as far as possible. The task was challengeable and
difficult due to the muddy and slippery terrain at some places.
CHAPTER 5
CONCLUSION
With the helpful regard of teacher and
cooperative behavior of all friends, all the work is complete as scheduled in
routine time assigned to us although we faced minor difficulties during our
orientation. The management team had arranged the required instruments and
accessories for our daily field work. This had made our work easy, reliable;
less time consuming and competitive. All the results we obtained were within
the limits given to us. This camp really helped us with the practical parts of
survey fieldwork as we were working in conditions we will surely have to face
in the future. It increased our confidence in handling instruments as well as
completing projects within given deadlines.
We
think I.O.E should organize such field works frequently and for all possible
subjects, as practical knowledge is better. In these field works, we gain first
hand concept of the subject matter that makes it easier for us to grasp the
concept. At last, this entire camp was very informative, effective and
enjoyable.
Any
suggestion and comment are heartily acceptable. During report preparation all
the confusions are cleared by teachers whom we are very grateful.
Add your Comments below